OpenAI's Project Camellia will construct a mega-scale AI datacenter park in Georgia with a total power demand of approximately 3.2 GW. The company signed a 25-year long-term power supply agreement with Georgia Power to ensure stable electricity supply. The datacenter park is planned to be phased into operation between 2028 and 2032, with the capability to provide up to 1 GW power capacity feedback to the grid during peak consumption.
OpenAI's 3.2 GW power commitment for a single datacenter park sets a new scale for AI infrastructure, locking long-term grid capacity.